POAC CMB minutes 2019-05-02
Date: 2019-05-02
Time: 09:00-10:00 CEST
Type of meeting: Gotomeeting (https://www.gotomeet.me/Paul_Simons)
Participants
Chair
Simons, Paul <paul.simons@codabox.com> as POAC Community Leader
Elected members (with voting right)
Allikas, Ahti <ahti.allikas@opuscapita.com>, OpusCapita
Bertocchi, Elisa <Elisa.Bertocchi@regione.emilia-romagna.it>, Regione Emilia-Romagna
Johansson, Magnus <magnus.johansson@digg.se>, Digg
Maroe, Jan <jan.andre.maroe@difi.no>, Difi
Observers (without voting right)
Birgisson, Georg <georg@midran.is>, Release Manager
Agenda
- Approval of the agenda
- Status of current development
- Decision on delay of release
- Next meeting
- Any other Business
Topics not discussed
- N/A
Information items
- Status of the current development of the validation artifacts given by Georg
- Siw is acting as dev
- Martin is acting as tester
- Last Tuesday, the conclusion was that quality of the deliverables is not good enough to proceed with releasing according the agreed plan
- Main reasons are
- Late arrival of the TC434 validation artefact deliverable
- This created issues on our development
- Automated tests are failing
- Due to the new release of the TC434 validation artefact deliverable
- Reported bugs
- Testing period took longer than foreseen
- Due to holiday period
- Due to other priorities
- Late arrival of the TC434 validation artefact deliverable
- In general the development has become more complex due to
- Layered approach adding complexity
- TC434 layer
- Country specific rules
- Layered approach adding complexity
- Proposed solutions to better align the different layers are
- Share each others RC's
- Better align the release dates for all layers
- To be discussed at later stage.
Decisions
- The CMB voted and agreed for a 2 week delay
- Publishing date set to May 15th
- Taking effect on May 29th
- Dates to be confirmed at the next CMB meeting
Action items
- Georg will take care of the communication of the decision
Next meeting
- May 8, 15.00-16.00 CET