RefGrp Workgroup Meeting 2023-04-03

Conclusions/decisions of the meeting

The RC is sent out. Comments came in and will be processed in the upcoming days.

DDTS work by the e-Dec community is done in the same timeline as the POAC activities.

DDTS was approved by the e-Dec CMB.

The public review is ongoing.

This is however not jeopardizing the overall timeline set to 01/07/2023.

The e-Dec CMB decided to change the name from DDTS to Wildcard scheme and it will be part of the Peppol policy of identifiers.

Versioning and version numbers is still looked at and how to use it in the document identifiers. This is part of the review.

No issues were raised for the Playground. Everything is running as expected.

The deadline for finishing tests has been set to 30/4/2023 allowing corner 4 testers enough time.

Multiple candidates came in to help testing. An overview with receivers will be made and send around to facilitate the testing.

If anyone needs an SMP account on the Playground, please log a ticket via the service desk.

People that do not have access to the Github repository shall send their account to Georg. A mail with invitation will be sent.

Information from previous meeting.

Oxalis is ready to be used for DDTS. Latest version is on Release Oxalis 5.3.0 · OxalisCommunity/oxalis

Philip Helger has adapted his solution as well. Contact him directly if you use his A.P. software.

 

Todo for next meeting(s)

  • Service providers shall communicate the most common scenarios they use to the corresponding PA. Goal is to have a realistic set of testcases. Slide 3 of the Agenda can be used as starting point. (All S.P.)

  • S.P. shall send an e-mail to paul.simons@codabox.com or georg@midran.is with the description of the test they want to execute.

  • Georg will create a page for each test.

     

Next meeting planned on 2023-04-17 09.00 - 10.00 CET