RefGrp Workgroup Meeting 2023-03-20

 

Conclusions/decisions of the meeting

The RC is sent out. Waiting for comments to come in.

DDTS work by the e-Dec community is done in the same timeline as the POAC activities.

There is a slight delay in the DDTS approval process. This is however not jeopardizing the overall timeline set to 01/07/2023

Versioning and version numbers is still looked at and how to use it in the document identifiers. This is part of the review.

Multiple improvements have been implemented on the playground. Everything is running as expected. An update of the schematrons is planned for later this week.

The deadline for finishing tests has been set to 31/4/2023 allowing corner 4 testers enough time.

We are still looking for new corner 4 testers.

Testing is going as expected so far.

Service providers shall communicate their scenarios to Paul and/or Georg to be able to prepare Github to track testing.

People that do not have access to the Github repository shall send their account to Georg. A mail with invitation will be sent.

Information from previous meeting.

Oxalis is ready to be used for DDTS. Latest version is on Release Oxalis 5.3.0 · OxalisCommunity/oxalis

Philip Helger has adapted his solution as well. Contact him directly if you use his A.P. software.

 

Todo for next meeting(s)

  • Service providers shall communicate the most common scenarios they use to the corresponding PA. Goal is to have a realistic set of testcases. Slide 3 of the Agenda can be used as starting point. (All S.P.)

  • S.P. shall send an e-mail to paul.simons@codabox.com or georg@midran.is with the description of the test they want to execute.

  • Georg will create a page for each test.

     

Next meeting planned on 2023-04-03 09.00 - 10.00 CET