RefGrp Workgroup Meeting 2023-05-15

Conclusions/decisions of the meeting

The RC of the datamodel was sent out. Comments came in and are being processed.

The public review is for the Wildcard scheme is ongoing.

This is however not jeopardizing the overall timeline set to 01/07/2023.

Versioning and version numbers is still looked at and how to use it in the document identifiers. This is part of the review but no progress yet.

No issues were raised for the Playground. Everything is running as expected.

The deadline for finishing tests has been set to 31/05/2023 allowing corner 4 testers enough time.

If anyone needs an SMP account on the Playground, please log a ticket via the service desk.

People that do not have access to the Github repository shall send their account to Georg. A mail with invitation will be sent.

There are 2 webinars scheduled by eDEC and PoAC to explain the impact of PINT on the Peppol members.

Todo for next meeting(s)

  • Service providers shall communicate the most common scenarios they use to the corresponding PA. Goal is to have a realistic set of testcases. Slide 3 of the Agenda can be used as starting point. (All S.P.)

  • S.P. shall send an e-mail to paul.simons@codabox.com or georg@midran.is with the description of the test they want to execute.

  • Georg will create a page for each test.

     

Next meeting planned on 2023-05-31 09.00 - 10.00 CET