The action log was created on June 14th, 2018. Open action items back to March 2018 were investigated and added to the list.

...

Start dateIDActionResponsible PersonDue date
(if applicable)
2018-05-251

Send out a call for candidate for one CMB member (to succeed Olav Kristansen, Difi) in mid June so that the new member can be elected.

Hans Berg


2018-05-252

Add edit restrictions to previous Confluence meeting minutes

Hans Berg
2018-05-253Ask Former user (Deleted) to attend a CMB to discuss/inform about
  • ISO6523 id inclusion in OpenPEPPOL: process
Hans Berg
2018-05-254TVR
  • integrate comment from public review etc.
    • PUBLIC_KEY of C2 required for PEPPOL AS4 profile
      • In the same formatting as provided in SMP
      • SENDER_CERTIFICATE key for SBDH
    • State that MLR SMP registration should not be considered
    • Annex on how to handle C4 validation
    • 2.5.5 add note on certificate change (Martin’s comment #4)
    • Comment Martin #5: severity MUST be failure, EBMS:0001, PEPPOL AS4 spec states, that participant check is needed -> same check here
    • 2.5.3: if negative TVR is received later than 2:30 than the problem must be resolved out-of-band

Philip Helger


2018-05-255

PEPPOL Directory: Trigger an information to all SMP providers (Oct 31st 2018) in accordance with Former user (Deleted) (according to decision # 3 in TICC CMB 2018-04-27 minutes)

Hans Berg
2018-05-256Billing BIS v3
  • Contact POACC on the usage of document type and process identifiers (and schemes) for Billing BIS v3
Philip Helger
2018-05-257

Draft a change request  (to agreement workgroup) for Annex 4 to remove hard coded references to technical specifications

Hans Berg
2018-05-2510

PEPPOL AS2 1.2 - SHA-256 support

Hans Berg asked the MC for approval on May 4 but not enough approvals were received. Hans Berg to re-ask MC for approval. Next MC meeting planned for June 12th, 2018.

That is also partially related to https://openpeppol.atlassian.net/projects/TICC/issues/TICC-44

Hans Berg2018-05-2511Non-XML Payload specification
  • Define real action items in next TICC CMB meeting
Hans Berg
2018-05-2513

Draft a proposal as commented in TICC-46.

Bård Langöy
2018-06-0817Draft a mandate for the Testbed v2 WorkgroupHans Berg2018-06-21
2018-06-0818Hans check with Anna-Lis Berg to respond to Maarten Daniels e-mail re: CEF vs PEPPOL AS4 profile (see completed Action #8)Former user (Deleted)
2018-06-1419AS2 version 1.2 specification with SHA-256 support must be drafted.Philip Helger






Completed actions


Start dateIDActionResponsible PersonDue date
(if applicable)
Completion date
2018-05-258PEPPOL AS4 vs. eSENS profile conformance
  • Philip Helger has distributed Sander's response to TICC CMB on May 2nd.
Philip Helger2018-05-022018-05-02
2018-05-259PEPPOL AS2 1.01 date of obligationHans Berg
2018-06-14
2018-05-2510

PEPPOL AS2 1.2 - SHA-256 support

Hans Berg asked the MC for approval on May 4 but not enough approvals were received. Hans Berg to re-ask MC for approval. Next MC meeting planned for June 12th, 2018.

That is also partially related to https://openpeppol.atlassian.net/projects/TICC/issues/TICC-44

Hans Berg

2018-05-2512New identifier issuing agenciesPhilip Helger
2018-06-14
2018-05-2514Consider introducing a global CMB decision log and action log to enable swift follow up of decisions and actions.TICC CMB
2018-06-14
2018-06-0815Testbed Taskforce: Call for participation to TICC members sent outHans Berg
2018-06-14
2018-06-0816Testbed: Draft a mandate for the Testbed v1 Task Force - by Monday, June 11thFormer user (Deleted)2018-06-112018-06-11






...