- News
- News from the Peppol network
- Open Tasks Philip Helger
- SMP 1.3.0 Update (Main document changes were done)
- create a migration plan for SMP 1.3.0 specification (gradual implementation on SMP side should work, no big bang)
- Get it out for review asap
- Provide a plan how to monitor SMP 1.3.0 implementation progress (based on Peppol Analytics)
- Collect comments
- Publish final version
- PPFUOI 4.2.0
- Create an impact analysis on PPFUOI 4.2.0 (in July)
- Finalize TICC-19
- SMP 1.3.0 Update (Main document changes were done)
- Activities for this year
- Published
- Progress alignment with change and release management based on new agreement change processes
- Continue Peppol specification upgrade based on latest version of underlying standard e.g., OASIS
- Commence work on future of SML – defining business requirements followed by solution implementation in due course
- Documentation of Peppol eDelivery Network Architecture
- Ensure and maintain safe & secure operation over Peppol eDelivery Network
- Resource problem is still pressing
- Ad activity 2: Discussion on the comparison of new and existing standards should be done in a less "ad hoc way"
- Start documenting findings in a more structured way
- Ad activity 3: Brainstorming for Peppol Architecure v2 has been started
- Check if a restricted Confluence page can be used instead
- Crosscheck with the long term tasks
- Published
- It was agreed, that eDEC will take over the responsibility of the existing MLR BIS
- We agreed to not change the publication location https://docs.peppol.eu/poacc/upgrade-3/profiles/36-mlr/ because it will be most likely replaced with MLS soon
- This means, that the MLS specification, as the proposed successor to MLR BIS, will also be maintained by eDEC
- Next meeting
- Thursday September 14th, 9:00 to 11:00 CEST
...